Abstract
Claims for additional costs and time extensions result from a variety of events occurring during the course of construction. To enhance the chances of success, contractors when submitting their claims must closely follow the steps stipulated in the contract conditions, by providing a breakdown of alleged additional costs and time with sufficient documentation. This paper aims to provide a better insight on the process of claims management in the Malaysian construction industry. It is reviewing the early part of the PhD research and hopefully the findings will try to generate means of improving the claims management process. With the proper claim management framework, it is hoped that contractors can utilize it to improve their claim management process in the future.
Keywords
References
- Abdul-Malak, M. A. U., Mustafa, A. M., El-Saadi, M. H. & Abou-Zeid, M. G. (2002). Process Model for Administrating Construction Claims. Journal of Management in Engineering, April 2002.
- Al Bawaba. (2005). UAE construction claims up to 10 times, available at: www.albawaba.com/en/countries/UAE/184821.
- Arditi, D. & Bhupendra, K. P. (2005). Selecting a Delay Analysis Method in Resolving Construction Claims. International Journal of Project Management , 24, 145–155
- Callahan, J. T. (1998). Managing Transit Construction Contract Claims. Synthesis of Transit Practice. Washington : National Academic Press
- Chovichien, V. & Tochaiwat, K. (2006). Information System for Managing Employer’s Construction Claims. Technology and Innovation for Sustainable Development Conference (TISD2006).
- Enshassi, A. & Mohamed, S. (2009). Problems Associated with the Process of Claim Management in Palestine. Journal of Engineering Construction and Architectural Management , 16, 61-72.
- Essam, K. Z. (2006). Construction Claims in United Arab Emirates: Types, Causes and Frequency. International Journal of Project Management, 24, 453-459.
- Hassanein, A. A. G. & El Nemr, W. (2008). Claims management in the Egyptian industrial construction sector. Engineering, Construction and Architectural Management , 15(3), 246-59.
- Ho S. P. & Liu, L. Y. (2004). Analytical model for analyzing construction claims and opportunistic bidding. Journal of Construction Engineering and Management , 130(1), 94–104.
- Hughes, G. A. & Barber, J. N. (1992). Building and Civil Engineering Claims in Perspective. London, Longman Scientific & Technical.
- Kangari, R. (1995). Construction claim documentation in arbitration. J. Constr. Engineering and Management ASCE , 121(2), 201-208.
- Kartam, S. (1999). Generic methodology for analyzing delay claims. Journal of Construction Engineering and Management , 125(6), 409-19.
- Khanchitvorakul, S. (2000). Development of Construction Claim Supporting System. Master of Engineering King Mongkut University of Technology Thonburi.
- Ren, Z. & Anumba, C. J. (2003). The Development of a Multi-Agent System for Construction Claims Negotiation. Journal of Advances in Engineering Software , 31, 683-696.
- Robert, K. C. (1997). Managing Change Orders and Claims. Journal of Management in Engineering, January.
- Semple, C., Hartman, F. T. & Jergeas, G. (1993). Construction claims and disputes: causes and cost/time overruns. J. Constr. Engrg. and Mgmt., ASCE , 120(4), 785-795.
- Sheikh S. J. A. A. S., Sami, M. F. & David, J. H. (2003). A database management system to document and analyse construction claims. Journal of Advances in Engineering Software , 34, 477–491
- Singh, A. & Sakamoto, I. (2001). Multiple Claims in Construction Law: Educational Case Study. Journal of Professional Issues in Engineering Education & Practice.
- Singh, P., Fook, C. Y. & Sidhu, G. K. (2006). A Comprehensive Guide to Writing a Research Proposal. Batu Caves: Venton Professional.
- Songseng, Y. & Jing, X. (2011). Construction Claims Management of Civil Engineering. Advanced Materials Research , 243-249, 6348-6351
- Spittler, J. R. & Jentzen, G. H. (1992). Dispute resolution: Managing construction conflict with step negotiations. AACE Transactions, D9, 1–10.
- Surawongsin, P. (2002). The Implementation of Construction Claims Management in the Thai Construction Industry, Master Thesis School of Civil Engineering Asian Institute of Technology[AIT], Pathumthani, 2002.
- Tochaiwat, K. (2006). An Analysis of the Employers’ Claim Management System in International Construction Projects. Proceeding of 11th National Convention of Civil Engineer, Phuket.
- Tochaiwat, K. & Chovichien, V. (2004). Strategic Data for Employers’ Claims. International Symposium on Globalisation and Construction: CIB-W107.
- Vidogah, W. & Ndekugri, I. (1997). Improving Management of Claims. Journal of Management in Engineering , 11(1), 58-63.
- Yates, J. K. (2006). Avoiding and Minimizing Construction Delay Claim Disputes in Relational Contracting. Journal of Professional Issues in Engineering Education and Practice , 3, 168-179
- Yogeswaran, K., Kumaraswamy, M. M. & Miller, D. R. A. (1998). Claims for extensions of time in civil engineering projects. Construction Management and Economics , 16(3), 283–93.
Downloads
No downloads have been recorded for this article yet. Figures appear here once readers begin downloading the full text.
How to Cite
Share this article
License
Copyright (c) 2013 Nor Azmi Bakhary, Hamimah Adnan, Azmi Ibrahim, Noor Akmal Adillah Ismail (Author)

This work is licensed under a Creative Commons Attribution 4.0 International License.
Author (s) should affirm that the material has not been published previously. It has not been submitted and it is not under consideration by any other journal. At the same time author (s) need to execute a publication permission agreement to assume the responsibility of the submitted content and any omissions and errors therein. After submission of revised paper in the light of suggestions of the reviewers, the editorial team edits and formats manuscripts to bring uniformity and standardization in published material.
This work will be licensed under Creative Commons Attribution 4.0 International (CC BY 4.0) and under condition of the license, users are free to read, copy, remix, transform, redistribute, download, print, search or link to the full texts of articles and even build upon their work as long as they credit the author for the original work. Moreover, as per journal policy author (s) hold and retain copyrights without any restrictions.
Keywords
Section
Published
Submissions
Have research to publish? Journal of Education and Vocational Research welcomes submissions.
Make a Submission