Abstract

This paper assesses the construction professionals’ perception on the major causes of construction project delays and there consequential effects of on the Lusaka – Zambia, construction industry. This is due to the fact that the Zambia construction industry is a major key sector in the development and economic growth of Zambia. Despite this belief, the industry has not escaped the challenges facing other countries worldwide in terms of construction projects performance with regards to the delivery of projects on time as stipulated in the contracts. Data used in this study were derived from both primary and secondary sources. The secondary data was collected through a detailed review of related literature. The primary data was collected through a structured questionnaire survey, distributed to construction professionals, who include: architects, quantity surveyors, builders, civil engineers, land surveyors and project managers. Out of the 50 questionnaires sent out, 32 were received back representing 64% response rate. The primary data from the questionnaires was analyzed using descriptive statistics procedures. Hence, findings from the study revealed that delay in progress payments, difficulties in financing projects by the contractor, delay in approving major changes in the scope of work amongst others, were the major causes of construction delays. The study also revealed that extension of project time and cost over runs are the two major effects of construction project delays in Lusaka, Zambia. The study contributes to the body of knowledge on the subject of the causes and the effects of delay construction project delays in Lusaka, Zambia.

Keywords

References

  • Aibinu, A. A. & Jagboro, G. O. (2012). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management , 20, 593–599. DOI: https://doi.org/10.1016/S0263-7863(02)00028-5
  • Aiyetan, A., Smallwood, J. & Shakantu, W. (2011). A systems thinking approach to eliminate delays on building construction projects in South Africa. Acta Structilia , 18(2). DOI: https://doi.org/10.38140/as.v18i2.115
  • Assaf, S. A. & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management , 24, 349–357. DOI: https://doi.org/10.1016/j.ijproman.2005.11.010
  • Ali, A. S., Smith, A. & Pitt, M. (n.d.). Contractors’ perception of factors contributing to project delay: case studies of commercial projects in klang valley, Malaysia: University of Malaya.
  • Alkhathami, M. M. (2004). Examination of the correlation of critical success and delay Factors in construction projects in the kingdom of Saudi Arabia: University of Pittsburgh.
  • Behboudi, S. F. (2009). A Model to predict the impact of Excusable and Non-Excusable Delays on selected residential construction projects: Carleton University. DOI: https://doi.org/10.1061/41002(328)41
  • Baki, M. A. (1999). Delay Claims Management in Construction-A Step-By-Step Approach: ProQuest Dissertations & Theses Full Text: pg. 36-38.
  • Haseeb, M., Xinhai, L., Aneesa Bibi, A. & Maloof-ud-Dyian, R. W. (2011). Causes and Effects of Delays in Large Construction Projects of Pakistan. Kuwait Chapter of Arabian Journal of Business and Management Review , 1(4).
  • Mohammed, K. A. & Isah, A. D. (2012). Causes of delay in Nigeria construction industry. Interdisciplinary journal of contemporary research in business , 4(2).
  • Mohamad, M. R. B. (2010). The factors and effect of delay in government Construction project, Case study in kuantan: University Malaysia Pahang.
  • Moser, C. A. & Kalton, G. (1971). Survey methods in social investigation. UK, Heinemann Educational.
  • Motaleb, O. & Kishk, M. (2010). An investigation into causes and effects of construction delays in UAE: Robert Gordon University.
  • National Council for Construction, Zambia. (2004). Development of contractor registration scheme with a focus on small scale civil works contractors: final report.
  • Pourrostam, T. & Ismail, A. (2011). Significant Factors Causing and Effects of Delay in Iranian Construction Projects. Australian Journal of Basic and Applied Sciences , 5(7), 450-456.
  • Rider, R. J. & Long, R. J. (2013). Analysis of Concurrent/Pacing Delay. New York: Long International Inc.
  • Sambasivan, M. & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management , 25, 517–526. DOI: https://doi.org/10.1016/j.ijproman.2006.11.007
  • Theodore, T. (2009). Types of Construction Delays. Understanding them clearly, analyzing them correctly. 2nd Edition. Oxford: Elsevier Inc. Pages 25-36. DOI: https://doi.org/10.1016/B978-1-85617-677-4.00002-7
  • Wei, S. K. (2010). Causes, effects and methods of minimizing delays in construction projects: Universiti Teknologi Malaysia.

Downloads

Full-text downloads recorded for this article, by month.

No downloads have been recorded for this article yet. Figures appear here once readers begin downloading the full text.

How to Cite

Aigbavboa, C., Thwala, W., & Mukuka, M. (2014). Construction Project delays in Lusaka, Zambia: Causes and Effects. Journal of Economics and Behavioral Studies, 6(11), 848-857. https://doi.org/10.22610/jebs.v6i11.544

Share this article

Section

Research Paper

Published

2014-11-30

Submissions

Have research to publish? Journal of Economics and Behavioral Studies welcomes submissions.

Make a Submission