Abstract
Despite myriad of research effort directed at improving the performance of construction projects, poor productivity, budget overruns, quality related issues, and schedule overruns have been recurring on most construction projects. As a consequence, time, cost and quality of construction, which are among the key project performance indicators (PPIs), have suffered poor performance in many construction project undertakings. While several studies have addressed these performance dependents parameters separately and collectively, the impact of political, environmental, social, technological, economical, and legal (PESTEL) related factors on the PPIs has however not been considered. The purpose of this study, therefore, is to identify PESTEL related factors, and further determine their impact on the PPIs in the South African construction industry. South African contractors, which are registered with the CIDB (Grades 5-9) were sampled and administered questionnaires to achieve the purpose of the study. The study determined that rework, poor planning, and inadequate training are most closely associated with poor performance of the PPIs. It is believed that addressing the areas of concern identified in this study would contribute to improved performance of the PPIs in South African construction, which would ultimately engender satisfaction of construction stakeholders.
Keywords
References
- Abdul‐Rahman, H., Yahya, I. A., Berawi, M. A. & Wah, L. W. (2008). Conceptual delay mitigation model using a project learning approach in practice. Construction Management and Economics , 26(1), 15-27.
- Abisuga, A. O., Amusu, O. R. & Salvador, K. A. (2014). Construction Delay in Nigeria: A Perception of Indigenous and Multinational Construction Firms. Journal of Emerging Trends in Economics and Management Sciences, 5(3), 371-378.
- Adebowale, O. J. & Fapohunda, J. A. (2015). Analysis of construction-related factors affecting the efficiency of construction labour, Journal of Construction Project Management and Innovation , 5(1), 1115-1130.
- Adebowale, O. J. & Smallwood, J. J. (2020). Qualitative model of factors influencing construction labour productivity in South Africa. Journal of Construction , 13(1), 19-30.
- Ahiaga-Dagbui, D. D. & Smith, S. D. (2014). Rethinking construction cost overruns: cognition, learning and estimation. Journal of Financial Management of Property and Construction , 19(1), 38-54.
- Aibinu, A. A. & Jagboro, G. O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management , 20(8), 593-599.
- Aichouni, M., Ait Messaoudene, N., Al-Ghonamy, A. & Touahmia, M. (2014). An empirical study of quality management systems in the Saudi construction industry. International Journal of Construction Management , 14(3), 181-190.
- Akinsiku, O. E. & Akinsulire, A. (2012). Stakeholders' Perception of the Causes and Effects of Construction Delays on Project Delivery. Journal of Construction Engineering and Project Management , 2(4), 25-31.
- Akogbe, R. K., Feng, X. & Zhou, J. (2015). Construction Projects Productivity in West African country of Benin: Case of Ground Earthworks. Journal of Construction Engineering and Project Management , 5(2), 1623.
- Alinaitwe, H. M., Mwakali, J. A. & Hansson, B. (2007). Factors affecting the productivity of building craftsmen‐studies of Uganda. Journal of Civil Engineering and Management , 13(3), 169-176.
- Ameh, O. J. & Osegbo, E. E. (2011). Study of relationship between time overrun and productivity on construction sites. International Journal of Construction Supply Chain Management , 1(1), 56-67.
- Arditi, D. & Pattanakitchamroon, T. (2006). Selecting a delay analysis method in resolving construction claims. International Journal of Project Management , 24(2), 145-155.
- Assaf, S. A. & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management , 24(4), 349-357.
- Bierman, M., Marnewick, A. & Pretorius, J. H. C. (2016). Productivity management in the South African civil construction industry-factors affecting construction productivity. Journal of the South African Institution of Civil Engineering, 58(3), 37-44.
- Borse, M. & Khare, P. (2016). Analysis of Cost and Schedule Overrun in Construction Projects, International Journal of Innovative Science, Engineering & Technology, 3(1), 383-386.
- Chan, A. P. & Chan, A. P. (2004). Key performance indicators for measuring construction success. Benchmarking: An International Journal , 11(2), 203-221.
- Chen, L. & Luo, H. (2014). A BIM-based construction quality management model and its applications. Automation in construction , 46, 64-73.
- Chingara, B. & Moyo, T. (2014). Factors affecting labour productivity on building projects in Zimbabwe. International Journal of Architecture, Engineering and Construction, 3(1), 57-65.
- Choudhury, I. (2009). The effect of political unrest on construction time for food grain warehouses in Bangladesh. Construction Management and Economics , 27(7), 619-624.
- Coka, E. (2013). Construction sector productivity needs closer scrutiny to unlock its vast growth potential productivity SA.
- Construction Industry Development Board (CIDB). ( 2012). The construction industry indicator summary results. P retoria: CIDB, 1-10.
- Cottle, E. (2014). Bargaining indicators, twenty years – A labour perspectives twenty years of transformation of the construction sector in South Africa since the end of Apartheid, labour research service, 139150.
- Dane, F. C. (2011). Evaluating research – methodology for people who need to read research, Sage publication ltd, Boston, United State.
- Dai, J., Goodrum, P. M. & Maloney, W. F. (2009). Construction craft workers’ perceptions of the factors affecting their productivity. Journal of Construction Engineering and Management , 135(3), 217-226.
- Delgado‐Hernandez, D. J., Bampton, K. E. & Aspinwall, E. (2007). Quality function deployment in construction. Construction Management and Economics , 25(6), 597-609.
- Doloi, H., Sawhney, A., Iyer, K. C. & Rentala, S. (2012). Analyzing factors affecting delays in Indian construction projects. International Journal of Project Management , 30(4), 479-489.
- Dudek-Burlikowska, M. (2011). Application of estimation method of customer’s satisfaction in enterprise focused on quality. Journal of Achievements in Materials and Manufacturing Engineering , 47(1), 83-96.
- Enshassi, A., Arain, F. & Al‐Raee, S. (2010). Causes of variation orders in construction projects in the Gaza Strip. Journal of Civil Engineering and Management , 16(4), 540-551.
- Forsythe, P. (2015). Monitoring customer perceived service quality and satisfaction during the construction process. Construction Economics and Building , 15(1), 19-42.
- Hossain, M. A. & Chua, D. K. H. (2014). Overlapping design and construction activities and an optimization approach to minimize rework. International Journal of Project Management , 32(6), 983-994.
- Hogg, R. & Tannis, E. (2009). Probability and statistical inferences. 8th ed. Upper Saddle River (NJ): Prentice Hall , New York, United States.
- Iyer, K. C. & Jha, K. N. (2005). Factors affecting cost performance: evidence from Indian construction projects. International Journal of Project Management , 23(4), 283-295.
- Jarkas, A. M. (2015). Factors influencing labour productivity in Bahrain's construction industry. International Journal of Construction Management , 15(1), 94-108.
- Josephson, P. E. & Chao, M. (2014). Use and non-use of time in construction of new multi-dwelling buildings in Sweden. International Journal of Construction Management , 14(1), 28-35.
- Kaliba, C., Muya, M. & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management , 27(5), 522-531.
- Kazaz, A., Manisali, E. & Ulubeyli, S. (2008). Effect of basic motivational factors on construction workforce productivity in Turkey. Journal of Civil Engineering and Management , 14(2), 95-106.
- Khoshgoftar, M., Bakar, A. H. A. & Osman, O. (2010). Causes of delays in Iranian construction projects. International Journal of Construction Management , 10(2), 53-69.
- Kukoyi, P. O., Osuizugbo, I. C., Yohanna, H. S., Edike, U. E. & Ohiseghame, I. E. (2020). Pre-Qualification of Selecting Construction Project Contractors Using Health and Safety Criteria. J ournal of Engineering, Project, and Production Management , 1-7.
- Kukoyi, P. O. & Smallwood, J. J. (2017). A qualitative study of Health and Safety (H&S) construction practices in Lagos. Journal of Construction Business and Management , 1(1), 1-7.
- Loushine, T. W., Hoonakker, P. L., Carayon, P. & Smith, M. J. (2006). Quality and safety management in construction. Total Quality Management and Business Excellence , 17(9), 1171-1212.
- Memon, A. H., Rahman, I. A., Abdullah, M. R. & Azis, A. A. A. (2011). Factors affecting construction cost in Mara large construction project: perspective of project management consultant. International Journal of Sustainable Construction Engineering and Technology , 1(2), 41-54.
- Nasir, H., Ahmed, H., Haas, C. & Goodrum, P. M. (2014). An analysis of construction productivity differences between Canada and the United States. Construction Management and Economics , 32(6), 595-607.
- Ng, S. T. & Zhang, Y. (2008). Optimizing construction time and cost using ant colony optimization approach. Journal of construction engineering and management , 134(9), 721-728.
- Odesola, I. A. & Idoro, G. I. (2014). Influence of Labour-Related Factors on Construction Labour Productivity in the South-South Geo-Political Zone of Nigeria. Journal of Construction in Developing Countries , 19(1), 93-109.
- Ofori, G., Hindle, R. & Hugo, F. (1996). Improving the construction industry of South Africa: a strategy. Habitat International , 20(2), 203-220.
- Panas, A. & Pantouvakis, J. P. (2010). Evaluating research methodology in construction productivity studies. The Built and Human Environment Review , 3(1), 63-85.
- Rane, N., Lopes, M. S., Raval, M. A., Rumao, M. D. & Thakur, M. P. (2017). Study of effects of labour productivity on construction projects. International Journal of Engineering Sciences and Research Technology , 6(6), 15-20.
- Rivas, R. A., Borcherding, J. D., González, V. & Alarcón, L. F. (2011). Analysis of factors influencing productivity using craftsmen questionnaires: Case study in a Chilean construction company. Journal of Construction Engineering and Management , 137(4), 312-320.
- SA, construction. (2013). Highlighting trends in the South African construction industry, Pwc 1st edition, 1-56.
- SA, construction. (2015). Highlighting trends in the South African construction industry, Pwc 3st edition, 1-44.
- Sambasivan, M. & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management , 25(5), 517-526.
- Sezer, A. A. & Brochner, J. (2014). The construction productivity debate and the measurement of service qualities. Construction Management and Economics , 32(6), 565-574.
- Simpeh, F., Mohamed, Z. & Hartmann, A. (2014). Importance-performance analysis for modeling maintenance prioritization in higher institutions. Journal of Construction Project Management and Innovation , 4(2), 976-989.
- Simpeh, F. & Shakantu, W. (2020). An on-campus university student accommodation model. Journal of Facilities Management , Emerald Publishing Limited , 1-17.
- The construction sector. (2010). World cup building and wood workers international, campaign for decent work, 1-62.
- Ugwu, O. O. & Haupt, T. C. (2007). Key performance indicators and assessment methods for infrastructure sustainability—a South African construction industry perspective. Building and Environment , 42(2), 665-680.
- Windapo, A. O. & Cattell, K. (2013). The South African Construction Industry: Perceptions of Key Challenges Facing Its Performance, Development and Growth. Journal of Construction in Developing Countries , 18(2), 65.
- Zimina, D., Ballard, G. & Pasquire, C. (2012). Target value design: using collaboration and a lean approach to reduce construction cost. Construction Management and Economics , 30(5), 383-398.
Downloads
No downloads have been recorded for this article yet. Figures appear here once readers begin downloading the full text.
How to Cite
Share this article
License
Copyright (c) 2020 Oluseyi Julius Adebowale, Patricia Omega Kukoyi, Iyabo Mercy Olagoke, Badmus Ademola (Author)

This work is licensed under a Creative Commons Attribution 4.0 International License.
Author (s) should affirm that the material has not been published previously. It has not been submitted and it is not under consideration by any other journal. At the same time author (s) need to execute a publication permission agreement to assume the responsibility of the submitted content and any omissions and errors therein. After submission of revised paper in the light of suggestions of the reviewers, the editorial team edits and formats manuscripts to bring uniformity and standardization in published material.
This work will be licensed under Creative Commons Attribution 4.0 International (CC BY 4.0) and under condition of the license, users are free to read, copy, remix, transform, redistribute, download, print, search or link to the full texts of articles and even build upon their work as long as they credit the author for the original work. Moreover, as per journal policy author (s) hold and retain copyrights without any restrictions.
Keywords
Section
Published in
Vol. 12 No. 4(J) (2020)
Governance, Fiscal Policy & Institutional Performance
View issue contents
Published
Submissions
Have research to publish? Journal of Economics and Behavioral Studies welcomes submissions.
Make a Submission